.. _release_process:
Release Process ###############
The Zephyr project releases on a time-based cycle, rather than a feature-driven one. Zephyr releases represent an aggregation of the work of many contributors, companies, and individuals from the community.
A time-based release process enables the Zephyr project to provide users with a balance of the latest technologies and features and excellent overall quality. A roughly 6-month release cycle allows the project to coordinate development of the features that have actually been implemented, allowing the project to maintain the quality of the overall release without delays because of one or two features that are not ready yet.
Each release period will consist of a development phase followed by a stabilization phase. Release candidates will be created during the stabilization phase.
.. figure:: release_cycle.svg :align: center :alt: Release Cycle :figclass: align-center :width: 80%
Release Cycle
.. note::
The milestones for the current major version can be found on the
`Official GitHub Wiki <https://github.com/zephyrproject-rtos/zephyr/wiki/Release-Management>`_.
Information on previous releases can be found :ref:`here <zephyr_release_notes>`.
Development Phase
A relatively straightforward discipline is followed with regard to the merging of patches for each release. At the beginning of each development cycle, the main branch is said to be open for development. At that time, code which is deemed to be sufficiently stable (and which is accepted by the maintainers and the wide community) is merged into the mainline tree. The bulk of changes for a new development cycle (and all of the major changes) will be merged during this time.
The development phase lasts for approximately five months. At the end of this time, the release owner will declare that the development phase is over and releases the first of the release candidates. For the codebase release which is destined to be 3.1.0, for example, the release which happens at the end of the development phase will be called 3.1.0-rc1. The -rc1 release is the signal that the time to merge new features has passed, and that the time to stabilize the next release of the code base has begun.
Stabilization Phase
Over the following weeks and depending on the release milestone, only stabilization,
cosmetic updates, bug fixes, documentation improvements, and new tests for
existing features are permitted. (See :ref:table <release_milestones> below).
On occasion, more significant changes and new features will be allowed, but such occasions are rare and require a TSC approval and a justification. As a general rule, if you miss submitting your code during the development phase for a given feature, the best thing to do is to wait for the next development cycle. (An occasional exception is made for drivers for previously unsupported hardware; if they do not touch any other in-tree code, they cannot cause regressions and should be safe to add at any time).
As fixes make their way into the mainline, the patch rate will slow over time. The mainline release owner releases new -rc drops once or twice a week; a normal series will get up to somewhere between -rc4 and -rc6 before the code base is considered to be sufficiently stable and the release criteria have been achieved at which point the final 3.1.0 release is made.
At that point, the whole process starts over again.
.. _merge_criteria:
Merge Criteria
.. figure:: img/img_release_activity.png :width: 663px :align: center :alt: Release Activity
All :ref:pr_requirements must be met.
Minimal of 2 approvals, including an approval by the designated assignee.
Pull requests should be reviewed by at least a maintainer or collaborator of each affected area; Unless the changes to a given area are considered trivial enough, in which case approvals by other affected subsystems maintainers/collaborators would suffice.
Four eye principle on the organisation level. We already require at least 2 approvals (basic four eye principle), however, such reviews and approvals might be unintentionally biased in the case where the submitter is from the same organisation as the approvers. To allow for project wide review and approvals, the merge criteria is extended with the guidelines below:
soc, :file:boards and :file:drivers/*/*.A minimum review period of 2 business days, 4 hours for trivial changes (see
:ref:review_time).
Hotfixes can be merged at any time after CI has passed and are excluded from most of the conditions listed above.
All required checks are passing:
.. _release_quality_criteria:
Release Criteria
The main motivation is to clearly have the criteria in place that must be met for a release. This will help define when a release is "done" in terms that most people can understand and in ways that help new people to understand the process and participate in creating successful releases:
Below is the high level criteria to be met for each release:
Tier 0 platformsBlocker bug process kicks in during the release process and is in effect after the feature freeze milestone. An issue labeled as a blocker practically blocks a release from happening. All blocker bugs shall be resolved before a release is created.
A fix for a bug that is granted blocker status can be merged to 'main' and included in
the release all the way until the final release date.
Bugs of moderate severity and higher that have impact on all users are typically the candidates to be promoted to blocker bugs
Contributors and member of the release engineering team shall follow these guidelines for release blocker bugs:
.. _release_milestones:
Release Milestones
.. list-table:: Release Milestones :widths: 15 25 100 25 :header-rows: 1
Releases
.. _release_process_lts:
Long-term support releases are designed to be supported and maintained for an extended period and are the recommended release for products and the auditable branch used for certification.
An LTS release is defined as:
Product Focused +++++++++++++++
Zephyr LTS is the recommended release for product makers with an extended support and maintenance which includes general stability and bug fixes, security fixes.
An LTS includes both mature and new features. API and feature maturity is documented and tracked. The footprint and scope of mature and stable APIs expands as we move from one LTS to the next giving users access to bleeding edge features and new hardware while keeping a stable foundation that evolves over time.
Extended Stabilisation Period +++++++++++++++++++++++++++++
Zephyr LTS development cycle differs from regular releases and has an extended stabilization period. Feature freeze of regular releases happens 3-4 weeks before the scheduled release date. The stabilization period for LTS is extended by 3 weeks with the feature freeze occurring 6-7 weeks before the anticipated release date. The time between code freeze and release date is extended in this case.
Stable APIs +++++++++++
Zephyr LTS provides a stable and long-lived foundation for developing products. To guarantee stability of the APIs and the implementation of such APIs it is required that any release software that makes the core of the OS went through the Zephyr API lifecycle and stabilized over at least 2 releases. This guarantees that we release many of the highlighted and core features with mature and well-established implementations with stable APIs that are supported during the lifetime of the release LTS.
API Freeze (LTS - 2)
All stable APIs need to be frozen 2 releases before an LTS. APIs can be extended with additional features, but the core implementation is not modified. This is valid for the following subsystems for example:
New APIs for experimental features can be added at any time as long as they are standalone and documented as experimental or unstable features/APIs.
Feature Freeze (LTS - 1)
No new features or overhaul/restructuring of code covering major LTS features.
Auxiliary features on top of and/or extending the base OS and advertised LTS features can be added at any time and should be marked as experimental if applicable
Quality Driven Process ++++++++++++++++++++++
The Zephyr project follows industry standards and processes with the goal of providing a quality oriented releases. This is achieved by providing the following products to track progress, integrity and quality of the software components provided by the project:
Compliance with published coding guidelines, style guides and naming conventions and documentation of deviations.
Static analysis reports
Documented components and APIS
Requirements Catalog
Verification Plans
Verification Reports
Coverage Reports
Requirements Traceability Matrix (RTM)
SPDX License Reports
Each release is created with the above products to document the quality and the state of the software when it was released.
Long Term Support and Maintenance ++++++++++++++++++++++++++++++++++
LTS releases are published every 2.5 to 3 years and are branched and maintained independently from the main tree for approximately 5 years after they were released.
Support is provided in three main phases:
Support for a given LTS release (LTS N) continues until the initial release of the LTS two versions ahead (LTS N+2). A final release of LTS N occurs shortly after the initial release of LTS N+2.
The list of currently supported LTS releases and their EOL dates can be found
:ref:here <supported_releases>.
.. figure:: lts.svg :align: center :alt: Long Term Support Release :figclass: align-center :width: 80%
Long Term Support Release
Changes and fixes flow in both directions. However, changes from main branch to an LTS branch will be limited to fixes that apply to both branches and for existing features only.
All fixes for an LTS branch that apply to the mainline tree shall be submitted to mainline tree as well.
An auditable code base is to be established from a defined subset of Zephyr OS features and will be limited in scope. The LTS, development tree, and the auditable code bases shall be kept in sync after the audit branch is created, but with a more rigorous process in place for adding new features into the audit branch used for certification.
This process will be applied before new features move into the auditable code base.
The initial and subsequent certification targets will be decided by the Zephyr project governing board.
Processes to achieve selected certification will be determined by the Security and Safety Working Groups and coordinated with the TSC.
Host Tools Support Policy
Python Version Policy
Zephyr tracks the Python upstream release schedule_ when determining its minimum supported Python
version.
The minimum supported version is selected to balance long-term support and practical availability in mainstream, actively supported Linux distributions (e.g. current Ubuntu LTS and Debian Stable releases).
A Python version is considered for removal when:
.. _Python upstream release schedule: https://devguide.python.org/versions/
Hardware Support Tiers
Release Procedure
This section documents the Release manager responsibilities so that it serves as a knowledge repository for Release managers.
Each release has a GitHub issue associated with it that contains the full checklist. After a release is complete, a checklist for the next release is created.
The following syntax should be used for releases and tags in Git:
Release [Major].[Minor].[Patch Level]
Release Candidate [Major].[Minor].[Patch Level]-rc[RC Number]
Tagging:
.. figure:: release_flow.png :align: center :alt: Releases :figclass: align-center :width: 80%
Zephyr Code and Releases
The final release and each release candidate shall be tagged using the following steps:
.. note::
Tagging needs to be done via explicit git commands and not via GitHub's release
interface. The GitHub release interface does not generate annotated tags (it
generates 'lightweight' tags regardless of release or pre-release). You should
also upload your gpg public key to your GitHub account, since the instructions
below involve creating signed tags. However, if you do not have a gpg public
key you can opt to remove the ``-s`` option from the commands below.
.. tabs::
.. tab:: Release Candidate
.. note::
This section uses tagging 1.11.0-rc1 as an example, replace with
the appropriate release candidate version.
#. Update the version variables in the :zephyr_file:`VERSION` file
located in the root of the Git repository to match the version for
this release candidate. The ``EXTRAVERSION`` variable is used to
identify the rc[RC Number] value for this candidate::
EXTRAVERSION = rc1
#. Post a PR with the updated :zephyr_file:`VERSION` file using
``release: Zephyr 1.11.0-rc1`` as the commit subject. Merge
the PR after successful CI.
#. Tag and push the version, using an annotated tag::
$ git pull
$ git tag -s -m "Zephyr 1.11.0-rc1" v1.11.0-rc1
#. Verify that the tag has been signed correctly, ``git show`` for the
tag must contain a signature (look for the ``BEGIN PGP SIGNATURE``
or ``BEGIN SSH SIGNATURE`` marker in the output)::
$ git show v1.11.0-rc1
#. Push the tag::
$ git push [email protected]:zephyrproject-rtos/zephyr.git v1.11.0-rc1
#. Send an email to the mailing lists (``announce`` and ``devel``)
with a link to the release
.. tab:: Final Release
.. note::
This section uses tagging 1.11.0 as an example, replace with the
appropriate final release version.
When all final release criteria has been met and the final release notes
have been approved and merged into the repository, the final release version
will be set and repository tagged using the following procedure:
#. Update the version variables in the :zephyr_file:`VERSION` file
located in the root of the Git repository. Set ``EXTRAVERSION``
variable to an empty string to indicate final release::
EXTRAVERSION =
#. Post a PR with the updated :zephyr_file:`VERSION` file using
``release: Zephyr 1.11.0`` as the commit subject. Merge
the PR after successful CI.
#. Tag and push the version, using two annotated tags::
$ git pull
$ git tag -s -m "Zephyr 1.11.0" v1.11.0
#. Verify that the tag has been signed correctly, ``git show`` for the
tag must contain a signature (look for the ``BEGIN PGP SIGNATURE``
or ``BEGIN SSH SIGNATURE`` marker in the output)::
$ git show v1.11.0
#. Push the tag::
$ git push [email protected]:zephyrproject-rtos/zephyr.git v1.11.0
#. Find the new ``v1.11.0`` tag at the top of the releases page and
edit the release with the ``Edit tag`` button with the following:
* Copy the overview of ``docs/releases/release-notes-1.11.rst``
into the release notes textbox and link to the full release notes
file on docs.zephyrproject.org.
#. Send an email to the mailing lists (``announce`` and ``devel``) with a link
to the release