docs/project-management-guide/6-planning-phase/README.md
The second phase of a PM² project is the Planning Phase. It begins with the Planning Kick-off Meeting and ends once all project plans have been developed and baselined, and an appropriate management and implementation approach has been established. Most of a project's artefacts are created during the Planning Phase.
| Artefact Type | Description |
|---|---|
| Management Plans (standard) | These plans define the various processes to be used (e.g. for Risk Management). PM² provides Management Plan templates along with guidelines on how to tailor and customise them to the project's context and needs. |
| Project Plans (specific) | These plans are specific to the project (e.g. the Project Work Plan) and are built according to the project needs and the team's analysis and experience. PM² provides templates and guidelines for these plans. |
| Other | |
| (domain specific) | These artefacts are specific to the project domain (e.g. system models for IT projects). PM² does not provide templates for these artefacts. |
The Planning Phase starts with an official Planning Kick-off Meeting, the aim of which is to:
At this early stage, past experiences, and especially Lessons Learned from previous similar projects, will significantly help the project team.
This Planning Kick-off Meeting should be planned and run effectively as it is critical that the project goals are well understood. PM² provides templates for the Meeting Agenda and the Minutes of Meeting (MoM).
| Key Participants | Description |
|---|---|
| Project Manager (PM) | Organises the meeting. |
| Project Core Team (PCT) | |
| Business Implementation Group (BIG) | |
| User Representatives (URs) | |
| Solution Provider (SP) | |
| Project Owner (PO) | |
| Business Manager (BM) | Required participants. |
| Project Manager Assistant (PMA) | |
| Project Support Office (PSO) | Required to attend (if part of the project). |
| Other project roles or stakeholders | Optional participation (as per the project's needs). |
Inputs
Steps
Before the Planning Kick-off Meeting:
During the Planning Kick-off Meeting:
After the Planning Kick-off Meeting:
| RAM (RASCI) | AGB | PSC | PO | BM | BIG | SP | PM | PCT |
|---|---|---|---|---|---|---|---|---|
| Planning Kick-off Meeting | I | A | C | S | C | C | R | C |
Outputs
The Project Handbook summarises the project objectives and documents the selected approach for achieving the project goals. It documents the Critical Success Factors (CSFs), defines the key controlling processes, the conflict resolution and escalation procedure, policies and rules, and the project mindsets.
The Project Handbook also documents the project governance roles and their responsibilities, and defines the plans necessary for managing the project as well as any methodology-tailoring decisions. The project goals and scope (found in the Initiating Phase documents) are key inputs to this artefact.
The Project Handbook is an important reference document for all project members and stakeholders, and along with the Project Work Plan, is the basis on which the project is managed and executed.
| Key Participants | Description |
|---|---|
| Project Manager (PM) | Prepares the Project Handbook. |
| Business Manager (BM) | Involved in defining the document's key elements. |
| Other project stakeholders | Review the Project Handbook. |
| Project Core Team (PCT) | Consulted in developing the document. |
Inputs
Guidelines
Steps
| RAM (RASCI) | AGB | PSC | PO | BM | BIG | SP | PM | PCT |
|---|---|---|---|---|---|---|---|---|
| Project Handbook | I | I | A | S | C | I | R | C |
Outputs
The main purpose of the Project Roles & Responsibilities section of the Project Handbook is to document the roles and responsibilities for the project. Any deviations from the standard PM² Roles & Responsibilities should be justified and documented, and any new roles defined with their responsibilities clearly described. Based on this, the Project Stakeholder Matrix can be tailored to the project and named people assigned to all project roles (preliminary information is taken from the Project Charter).
PM² suggests several Project Management Plans (artefacts) which outline the various project management processes. These plans identify how an organisation manages relatively standard processes. These plans are the:
Depending on the organisation and the project, different levels of documentation detail may be required. When sufficient, a brief definition of each management process or plan can be provided in the Project Handbook. When a more extensive and detailed description is needed, separate management plans can be instituted based on the PM² templates and guidelines provided.
PM² defines a set of recommended project plans, which can be used for any type of project and provides templates and guidelines for each. However, in contrast to the standard Management Plans, which only require light customisation and tailoring, the Project-Specific Plans usually require more effort because their content is specific to the project.
The optimal level of detail included in Project-Specific Plans depends on the type, size and complexity of the project, the project management context and environment, and the experience and competences of the project team.
All Project-Specific Plans to be used in a project should be listed in the Project Handbook.
These plans are specific to the project domain (i.e. the project type) and are very often an integral part of the project planning and the overall project documentation. No templates are provided by PM².
However, the artefacts should still be identified and listed in the Project Handbook, as they are part of the project's planning-phase outputs. Examples of domain-specific artefacts include system designs (for IT projects), architectural layouts (for renovation/moving projects) and laws/policies (for policy projects).
6.2.5 Other
Escalation Procedure: An escalation procedure and tolerances should be defined (and tailored) in the Project Handbook. This should be referenced by the Management Plans to ensure that a consistent approach is applied.
The purpose of the escalation procedure is to provide an agreed and effective way for escalating issues and decisions when this is required. For example, it documents how important issues can be raised to a higher level of management for resolution. This ensures that the appropriate level of management is involved (or at least informed) if an issue cannot be resolved at a lower level.
Resource Needs: The Project Handbook must also define how the resources (people and equipment) allocated to the project will be used to serve the project's best interests.
As the work to be done becomes clearer, the skills needed to perform the work will also have to be recorded in the Project Handbook. A Training Plan can be annexed to the Project Handbook if personnel need to be trained in missing skills. If more people with these skills need to be hired, the hiring process must be described in the same section of the Handbook. Finally, the way resources will be released at the end of the project (or when their work is complete) must also be formalised here.
The Project Stakeholder Matrix lists all (key) project stakeholders and their contact details and clearly states their role(s) in the project. It may also include a classification or categorisation of each stakeholder. The information captured in the Project Stakeholder Matrix should be tailored to the project's needs.
| Key Participants | Description |
|---|---|
| Project Manager (PM) | Prepares the Project Stakeholder Matrix. |
| Business Manager (BM) | Assists the Project Manager (PM), particularly with the identification of |
| stakeholders on the client side. | |
| Other project stakeholders | Consulted on the identification of stakeholders. |
Inputs
Guidelines
PM² provides a Project Stakeholder Matrix template. The template includes the standard project roles organised into the following groups:
Note: Be careful to respect all applicable regulations on privacy and personal data rights when establishing and handling the Project Stakeholder Matrix.
Steps
| RAM (RASCI) | AGB | PSC | PO | BM | BIG | SP | PM | PCT |
|---|---|---|---|---|---|---|---|---|
| Matrix | I | I | A | S | C | I | R | C |
| Related Artefacts | Initiating | Planning | Executing | Monitor & Control | Closing |
|---|---|---|---|---|---|
| Stakeholder | |||||
| Management | Business Case | ||||
| Project Charter | Project Handbook | ||||
| Outsourcing Plan | |||||
| Communications | |||||
| Management Plan | Project | ||||
| Reports | Project Logs | ||||
| Stakeholders | |||||
| Checklist | Project-End | ||||
| Report |
Outputs
The Project Work Plan further elaborates the project scope and identifies and organises the project work and deliverables needed to achieve the project goals. It establishes a basis on which to estimate the project's duration, calculate the required resources, and schedule the work. Once the tasks are scheduled, the Project Work Plan is used as a basis for monitoring progress and controlling the project. The Project Work Plan should be baselined but also kept up-to-date during the life of the project and capture all project related work as identified during planning phase or emerged during the executing phase (e.g. risks, issues, corrective actions etc.)
| Key Participants | Description |
|---|---|
| Project Manager (PM) | Coordinates all activities in the development of the Project Work Plan. |
| Project Core Team (PCT) | Assists the Project Manager (PM). |
| Project Support Office (PSO) | May provide technical advice (e.g. for scheduling). |
Inputs
Steps
The Project Work Plan is composed of three parts:
| RAM (RASCI) | AGB | PSC | PO | BM | BIG | SP | PM | PCT |
|---|---|---|---|---|---|---|---|---|
| Project Work Plan | I | A | C | S/C | C | C | R | S/C |
| Related Artefacts | Initiating | Planning | Executing | Monitor & Control | Closing |
|---|---|---|---|---|---|
| Schedule and Cost | |||||
| Management | Business Case & | ||||
| Project Charter | Project Work Plan. | ||||
| (Work Breakdown, Effor | |||||
| & Costs, Schedule) | Project | ||||
| Reports | Project Work Plan | ||||
| Project Logs | Project-End | ||||
| Report |
Outputs
The objective of this section of the Project Work Plan is to break the project down into smaller and more manageable components such as deliverables, work packages, activities and tasks. The breakdown has multiple levels, each with progressively more detailed deliverables and work. Taken together, these define the project output(s) and the work involved in producing them (see Appendix C).
Inputs
Outputs
The objective of this section of the Project Work Plan is to estimate the effort needed for each project task identified in the Work Breakdown based on resource availability and capabilities. After a task is assigned to a resource (or to a resource profile) it also becomes possible to calculate its cost. The estimates will be an input for the creation of the schedule (see Appendix C).
Inputs
Outputs
6.4.3 Project Schedule
The objective of this section of the Project Work Plan is to document the dependencies between tasks, pinpoint their start and end dates, and work out the overall project duration. Detailed scheduling can be done for the entire project upfront, or alternatively, worked out (in adequate detail) only for some early parts of the Executing Phase, and then progressively developed in full detail. The Project Manager (PM) uses the schedule to authorise, coordinate and accept project work, and to monitor overall progress (see Appendix C).
Inputs
Outputs
The Outsourcing Plan defines the what and how for any outsourced products or services. It outlines the scope of products and/or services to be purchased or contracted, identifies the outsourcing strategies that will be used, and defines the relevant responsibilities for the full outsourcing lifecycle. Note that the present plan should be compliant with the relevant organisational rules and procedures.
| Participants | Description |
|---|---|
| Project Manager (PM) | Prepares the Outsourcing Plan. |
| Solution Provider (SP) | Reviews the plan. |
Inputs
Steps
| RAM (RASCI) | AGB | PSC | PO | BM | BIG | SP | PM | PCT |
|---|---|---|---|---|---|---|---|---|
| Outsourcing Plan | A | C | C | C | I | S | R | I |
| Related Artefacts | Initiating | Planning | Executing | Monitor & Control | Closing |
|---|---|---|---|---|---|
| Outsourcing Management | Project | ||||
| Charter | Project Handbook | ||||
| Outsourcing Plan | Project Reports | Project Logs | Project-End | ||
| Report |
Outputs
Deliverables acceptance planning aims to increase the likelihood that deliverables will be accepted by the client side and that the resources involved in the acceptance will be used in an efficient way.
The Deliverables Acceptance Plan documents the agreed criteria and approach for deliverables acceptance. It also documents the relevant responsibilities, including all activities and effort required, as well as the timing and capability requirements for this so that the project's deliverable(s) can be formally accepted by the client based on objective criteria and predefined timelines.
| Key Participants | Description |
|---|---|
| Project Steering Committee (PSC) | Approves the Deliverables Acceptance Plan. |
| Project Manager (PM) | Prepares the Deliverables Acceptance Plan. May be supported by |
| other roles such as the Project Quality Assurance (PQA), the Project | |
| Support Office (PSO), and other project stakeholders. | |
| Business Manager (BM) | Reviews and validates the deliverables acceptance requirements, |
| activities and associated metrics. |
Inputs
Guidelines
Steps
| RAM/RASCI | AGB | PSC | PO | BM | BIG | SP | PM | PCT |
|---|---|---|---|---|---|---|---|---|
| Deliverables Acceptance Plan | I | A | C | S | I | C | R | C |
| Related Artefacts | Initiating | Planning | Executing | Monitor & Control | Closing |
|---|---|---|---|---|---|
| Acceptance Management | Project | ||||
| Charter | Deliverables | ||||
| Acceptance Plan | Deliverables | ||||
| Acceptance | |||||
| Note | Deliverables | ||||
| Acceptance Checklist | |||||
| Decision Log | Project- | ||||
| End | |||||
| Report |
Outputs
The Transition Plan defines the goals, prerequisites, activities and responsibilities associated with transitioning from the old (pre-project) to the new (post-project) state. It seeks to minimise the impact of any disruptions on the business during the transition period, and to facilitate the roll-out of project outputs in a smooth and timely fashion, allowing them to be used efficiently and with no serious transition issues.
A successful transition is an important prerequisite for achieving the planned project benefits. All transition activities become part of the Project Work Plan and are scheduled and controlled as part of the overall project.
| Key Participants | Description |
|---|---|
| Project Manager (PM) | Prepares the Transition Plan. |
| Project Core Team (PCT) | Consulted in the plan's preparation. |
| Other project stakeholders | Review and approve the Transition Plan. |
Inputs
Steps
| RAM/RASCI | AGB | PSC | PO | BM | BIG | SP | PM | PCT |
|---|---|---|---|---|---|---|---|---|
| Transition Plan | I | A | C | C | C | C | R | C |
| Related Artefacts | Initiating | Planning | Executing | Monitor & Control | Closing |
|---|---|---|---|---|---|
| Implementation | |||||
| Management | Project | ||||
| Charter | Business Implementation Plan | ||||
| Transition Plan Project Work Plan | Project | ||||
| Reports | Transition Checklist | ||||
| Business Implementation Checklist | Project-End Report |
Outputs
The Business Implementation Plan aims to increase the likelihood of achieving the project's desired outcomes and benefits. It documents an assessment of the project's impact on the organisation's processes, culture and people and outlines the change-management and communications activities that need to take place to ensure that the project outputs are effectively integrated into the organisation's environment.
Depending on the organisation, the business implementation activities can be performed as part of the same project or as a separate one. These activities become part of the Project Work Plan and are scheduled and controlled as part of the overall project.
| Key Participants | Description |
|---|---|
| Business Manager (BM) | Prepares the Business Implementation Plan. |
| Project Manager (PM) | Assists the Business Manager (BM). Updates the Project Work |
| Plan to include all business implementation activities that fall | |
| within the scope and timeframe of the project. | |
| Business Implementation Group | |
| (BIG) and other project stakeholders | Consulted during the impact analysis and involved in the business |
| implementation activities. | |
| Project Owner (PO) | Reviews and approves the Business Implementation Plan. |
Inputs
Steps
| RAM (RASCI) | AGB | PSC | PO | BM | BIG | SP | PM | PCT |
|---|---|---|---|---|---|---|---|---|
| Business Implementation Plan | I | I | A | R | C | I | S | I |
| Related Artefacts | Initiating | Planning | Executing | Monitor & Control | Closing |
|---|---|---|---|---|---|
| Implementation | |||||
| Management | Project | ||||
| Charter | Business | ||||
| Implementation Plan | |||||
| Transition Plan | |||||
| Project Work Plan | Project | ||||
| Reports | Transition Checklist | ||||
| Business Implementation | |||||
| Checklist | Project-End Report | ||||
| (Post-Project | |||||
| Recommendations) |
Outputs
This is the second phase gate. A review and approval are recommended before the project can formally move to the next phase. The Project Manager (PM) uses the outputs of the Planning Phase to assess whether the goals of this phase have been achieved, and then requests approval from the Project Steering Committee (PSC) to move on to the Executing Phase.
If major deviations from the approved Business Case and/or Project Charter are identified, then the Project Steering Committee (PSC) must receive an additional approval from the Appropriate Governance Body (AGB) before the project can move on to the Executing Phase.
PM² provides a template Phase Exit Review Checklist for each phase that can be used by the Project Manager (PM) to guide the assessment, alongside a review of the phase's specific goals.
following table shows the strongest relations of moral virtues to key professional competencies.