--instructions--

Read the text and answer the question below.

--questions--

--text--

After talking with James, Jessica clarified the project timeline and shared it with the team:

Updated Project Timeline

Hi team,

We've updated our project timeline after reviewing the schedule.

The first phase is finalizing the software requirements, which should be done by Friday, March 7, 2025. In the second phase, we have ten development tasks. One important task is setting up the core database, as many other parts depend on it. This development phase will run from March 10 to April 4, 2025. The third phase is all about initial testing, and we aim to finish it by April 30, 2025. Finally, in the last phase, we'll spend two weeks on beta testing and fixing any critical issues. The final task in this phase is preparing the deployment documentation, which should be ready by May 16, 2025.

Let me know if you have any questions or need help with your part of the plan.

Best,

Jessica

By what date should the deployment documentation be ready?

--answers--

April 30, 2025

--feedback--

April 30 is the deadline for initial testing, not the final documentation.


March 10, 2025

--feedback--

March 10 is the start of the development phase, not the end of the project.


May 1, 2025

--feedback--

This date falls in the middle of the beta testing phase — May 16 is the final deadline.


May 16, 2025

--video-solution--

4

--explanation--

Focus on the sentence that starts with The final task in this phase is....

Jessica mentions that the final task of the last phase is preparing the deployment documentation, which should be ready by May 16, 2025.