Baseline

  • Jan 11, 2023

Baselines allow you to compare planned task dates and the current task progress.

The table below lists the main members that affect element appearance and functionality.

CharacteristicsMembers
VisibilityGanttView.ShowBaseline
Summary TaskGanttView.SummaryTaskBaselineStyle, GanttView.PrintSummaryTaskBaselineStyle
TaskGanttView.TaskBaselineStyle, GanttView.PrintTaskBaselineStyle
MilestoneGanttView.MilestoneBaselineStyle, GanttView.PrintMilestoneBaselineStyle