Use this page to decide how much planning a change needs. The answer turns on one question: is the intent already well defined? If it is, feed it to bmad-spec, which shapes it to the size of the work, and build. If it is not, the other pages in this chapter are how you get a defined intent. If the work belongs to an organization, with a PRD other people must approve and several engineers building in parallel, read Plan Inside an Organization first; it says how this chapter fits the process you already have.

Start from the Intent

A well-defined intent says what should be true when the work is done, what must not change, and what is out of scope: complete enough that someone else could build it without guessing, and no longer than that. Where it came from does not matter: a sentence, an issue, a forged idea, a research report, a PRD.

Keep the input short. bmad-spec reads everything you give it in one pass, and the practical ceiling is a few tens of thousands of tokens, roughly a 40-page document. Hand it a pile of raw documents several times that size and it silently loses the parts that mattered; condense them first. If the spec says the input is too thin, you are not done on this chapter yet.

  • Well-defined intent: run bmad-spec with it. A spec that fits one Build session goes straight to bmad-build; an epic-sized one gets Story Breakdown and a Build per story. See Define Requirements and a Specification.
  • Anything else: the intent is not ready yet. Use the pages below until it is, then run bmad-spec. The spec skill writes the contract; it does not help you figure out what you want.

If the change fits one implementation session, you are on the Build page's territory, not this chapter's: Build a Change covers sizing a session and whether a small change needs BMad at all.

:::note[Prerequisites] Install BMad before using Build or another BMad workflow. You don't need BMad for an obvious, low-risk edit. :::

Get to a Well-Defined Intent

These are independent tools, not stages. Pick the ones the gap calls for, in any order. None of them build anything. Condense what they produce and hand bmad-spec the result, not the raw pile.

The intent is missingDo this
A clear idea at all, or confidence the idea is goodExplore and Validate an Idea
Evidence a decision should rest onResearch a Decision
A written account of what the product is, for a PRD or a pitchA brief or PRFAQ: Define Requirements and a Specification
Shared decisions several epics or agents must followDesign UX and Architecture
Agreement, ownership, and sign-off among several people or teamsA PRD as the document the organization owns: Plan Inside an Organization

A short list of decisions is often enough on its own. You need a PRD when more than one person must agree on what the product is, or more than one epic must not diverge; otherwise skip it. A multi-epic product runs bmad-spec once per epic with those documents as sources.

Planning Skills and What They Produce

Every skill in this chapter writes a document you can hand on. The table runs from analysis through planning to solutioning; each chapter page is linked from the first skill it covers and explains when its skills fit. In an installed project, bmad-help recommends the next one.

SkillPurposeProduces
bmad-brainstormingGenerate ideas with a facilitated session (Explore and Validate an Idea)brainstorm.html keepsake plus an optional brainstorm-intent.md
bmad-forge-ideaPressure-test an idea until it hardens, proves out, or dies cheaplyforge-report.html every run; forged-idea.md when the idea hardens
bmad-deep-reconResearch a subject to support a decision (Research a Decision)Cited research.md plus an optional HTML briefing
bmad-product-briefCapture the product vision when the concept is clear (Define Requirements and a Specification)brief.md + addendum.md
bmad-prfaqStress-test a product concept customer-first, working backwards from the press releaseprfaq-<project>.md
bmad-prdCreate, update, or validate a PRDCreate/update: prd.md, addendum.md, .memlog.md; validate: HTML + .md report
bmad-uxRecord how the product looks and behaves (Design UX and Architecture)DESIGN.md, EXPERIENCE.md, .memlog.md
bmad-specCondense any intent into a short contract; break it into stories on requestSPEC.md + companions under specs/spec-<slug>/; optional stories.yaml
bmad-architectureMake the technical decisions that keep separately built parts consistentARCHITECTURE-SPINE.md by default
bmad-create-epics-and-storiesBreak requirements into epics and stories (Break Work into Stories and Track It)Epic files with stories
bmad-sprint-planningCheck readiness before implementation, then track story statusPASS/CONCERNS/FAIL + sprint-status.yaml

bmad-prd has three intents, create, update, and validate; say which one you want when you invoke it, or it will ask. bmad-product-brief feeds bmad-prd, which reads the brief during discovery, but neither requires the other.

Size Follows the Intent

The size of the intent decides how many Build sessions follow. One coherent outcome that needs several sessions is an epic. Work that spans several epics, or likely needs roughly 20 or more sessions, is a project. Scope is only one signal: use more planning when the work has high risk, unclear requirements, broad architectural reach, cross-system effects, or coordination between people or teams.

Every path uses the same implementation unit. Larger work adds shared context around that unit and repeats it; it does not switch to a separate delivery system.

Run the Path

1. Start Epic-Sized Work

Use this path when the work needs several Build sessions but still has one coherent outcome.

Define and divide the epic

  1. Run bmad-spec with the epic intent. See Define Requirements and a Specification for what a spec contains and when it is enough on its own.
  2. Ask for Story Breakdown. This creates the ordered stories.yaml beside SPEC.md.
  3. Review the proposed order and decide which stories need a checkpoint.

The story list is an execution plan, not a promise that nothing will change. Update the spec and re-run Story Breakdown when earlier work reveals a missing constraint, a better division, or a conflict between stories.

Establish the implementation pattern

Implement important, risky, or foundational stories with bmad-build. Early stories often settle the architecture, initial project structure, and repeated patterns that later stories will follow. Give those decisions human attention before automating repetitions of them.

Run Build once per story. Build creates or resumes that story's implementation record under the spec folder and keeps it linked to the parent spec.

Finish the epic

Verify the stories together, not only one at a time. Then run bmad-retrospective with the spec folder. Retrospective reads stories.yaml as the epic inventory and judges the combined result against the parent spec. See Finish an Epic.

2. Start Project-Sized Work

Use the full BMad flow for a greenfield product, a multi-epic initiative, or work likely to need roughly 20 or more implementation sessions.

Prepare only the planning the project actually needs from the table above (Plan Inside an Organization covers who owns which document and where sign-off happens). Then run bmad-spec per epic, track the stories with Break Work into Stories and Track It, and close each epic with Finish an Epic.

These documents coordinate implementation. They do not replace Build. Each epic still becomes a sequence of one-session units. Independent epic streams can proceed in parallel when their boundaries are explicit. Each stream needs an owner, and all streams stay accountable to the same product intent and architecture. Run integration checks and a retrospective at each epic boundary.

Dividing work can lose information: a requirement weakens, a constraint disappears, or two correct stories fail when combined. The PRD, architecture, and specs exist so later sessions can still see the whole.

After Decisions Stabilize

bmad-build-auto runs one session without waiting for human input. It does not choose the next story or own the backlog. Use it after the important implementation decisions are stable. For the worker contract, see Autonomous Development Loops.

What You Get

A path sized to the work: a spec and stories for an epic, or shared product documents plus one spec per epic for a project — each still implemented one Build session at a time.